Work and road closures

Roadworks and road closures in and around Son en Breugel can be found here. 

Dead and unsafe trees removed - starting Oct. 14

What: Removal of dead and unsafe trees
Where: various locations in Son en Breugel
When: starting October 14, 2026

Details

On Wednesday, October 14, 2026, we will begin removing approximately 50 trees at various locations in Son en Breugel. The trees have died or are unsafe. The trees are being removed to prevent unsafe situations
. The trees have been marked with a purple/pink cross.
We will be removing a large number of trees on Aziëlaan. These are trees that suffered greatly during the extremely wet period in 2024.

Locations

Cleaning street drains - starting in week 46

What: Cleaning street drains
Where: Main roads in Son en Breugel
When: Starting in week 46

Details

Starting in week 46, Adriaans Riolering- en Ontstoppingsbedrijf, based in Mierlo, will begin cleaning the storm drains on the main roads. The work will take several weeks.

The function of a gully is to drain rainwater that falls on roads and sidewalks. Leaves, sand and litter can end up in the gullies. This dirt is removed during the cleaning round. 

Note

We regularly find trash, bags of dog waste, and cement—from construction projects, for example—in the manholes. These items do not belong in the sewer system! They can cause clogs and/or force us to replace the manhole.

Grid reinforcement Son en Breugel: work in neighborhoods

What: Replacing and upgrading power lines in Son and Breugel
Where: In the neighborhoods in Son and Breugel.
When: as of April 2025 

Details

Enexis Netbeheer is going to expand the power grid in Son en Breugel. Together we are generating more and more sustainable energy with, among other things, solar panels and we are using more power for electric cooking, electric driving or a heat pump. Not only in Son & Breugel, but throughout the Netherlands. The electricity grid as constructed in the past is not equipped for this. This requires new, stronger cables in the ground. Enexis is proactively expanding the power grid to prevent problems. We call this 'network reinforcement'. By strengthening the grid, the electricity supply remains reliable and safe for residents and businesses. Enexis and the municipality are working together on this. The work will be carried out by Hurkmans and Hanab.

New power cables have been laid from Thermaelaan in Son to Ekkersweijer in Best. At the spot where the extra power cables are being laid, the forest edge will be rearranged at the same time and thus considerably improved.

From April 2025, part of the power grid in the neighborhoods in Son and Breugel will also be replaced and expanded. The work consists of:

  • Improving or renovating existing power houses. This is done inside the power houses and is not visible from the outside;
  • The installation of new power houses;
  • Excavation to replace and reinforce cables, in the street and under the sidewalk. 

All work can be tracked via the Bouwapp. Download the Bouwapp from the Google Play Store or App Store.